The Andalusian out to tender treatment plant Huércal-Overa

H-Odepuradora

The Ministry of Environment will invest 5.589.500,35 euros in building the wastewater treatment plant in the municipality of Almeria.

Total has set a deadline of 26 months by the Environment Agency and water.

The Ministry of environment and spatial planning, He has brought to tender the project design and execution of work of enlargement of the WWTP of Almeria municipality of Huércal-Overa.

The regional administration has set a tender base budget without VAT, that the asciende 5.589.500,35 euros. The implementation period marked by the Andalusian is 26 months, which differ by 20 months for the execution of the work and 6 months for commissioning.